| Testing the
casing:
After primary cementing any casing strings, drilling should not be resumed until a
time lapse of
eight (8) hours under for the conductor casing string and twelve
(12) hours under pressure for all other strings.
Cement is considered under pressure if one or more float valves are employed and are
shown to be holding the cement in place or when other means of holding pressure are used.
After cementing and prior to drilling the plug, all
casing strings, except the drive or structural casing, must
be pressure tested.
The conductor casing should be tested to a minimum pressure
of two hundred fifty (250) pounds per square inch (psi).
All other casing strings should be pressure
tested to fifty percent (50%) of the specified minimum
internal yield strength of the weakest section of the casing
string.
However a pressure test may be limited by hydrostatic
pressures based on internal and external mud weights.
All pressure tests are to be held for fifteen (15)
minutes. from the time the test pressure is accomplished and
not from the time the pump is kicked in.
If during this test period the pressure declines
more than ten percent (10%) of the initial test pressure or
if any other indications of a leak are found, the casing
should be re-cemented, repaired, or an additional casing
string run.
Should this be
the case, the casing needs to be re-tested
in the same manner as prescribed before.
The above
procedures should be repeated until a satisfactory test is
obtained. Any casing pressure tests should be recorded
in the daily drilling report
As already
explained in other sections, a casing string may possibly
be cemented in more than one stage. In such a case each
section must be tested as individual section.
However with
the possibility of the drive or conductor string, most
casing strings will have a minimum of two tests.
The first section being from surface to the float collar. The hole should
be clean out of any excess cement used on top of the collar and plugs and a
test made before drilling out the float..
The second test will be that of the shoe track. The cement should be
cleaned out too within five feet of the shoe and a second test
completed.
Some points to note: This is a good time to check both the casing tally
and the drilling assembly tally. Any differential between the two can be
picked up at this point and the necessary action taken. Drilling out the shoe
by mistake is not only an indication of amateurism but dangerous.
Before drilling the float is also a good time to perform drills that
can not be conducted with an open hole. Such drills as Stripping techniques,
Choke formalizations. This would be a good time to check the pump efficacy if
it has not been checked
From the time any obstruction is tagged, be it cement or a plug the instrumentation
equipment must functioning and recording as this will set the trend
such as the rate of penetration
Early It was mentioned knowing the distance from the float collar and the
shoe and comparing tally's The probability of both tally's agreeing are slim
as many factor can change the string length. Being 10 to 15 feet out is command
and is not a problem. What can not change is the distance between the float
and shoe. Once the float is engaged it is impossible to drill out the shoe by
mistake.
Drills and training are never down time or a wasted time. They
are good oil field practice and common sense. Do Them
All things being equal and have checked out we can not take out the shoe.
The shoe must be approached with caution and once drilled a flow check made.
Any remaining cement should be cleaned out and a short section of new hole
drilled before the hole is circulated clean in preparation for the Leak
off or formation integrity test. "read leak off testing under well
control"
|